Update July 11th

Wolfgang deficiencies have been identified on units 21-24 on Sunday. Please leave the green tape up as we fix these. Painting on units 25-28 is wrapping up. We have started painting on units 29-32.

Pressure washing is complete up to unit 40. We will begin pressure washing 41 to 44 starting on Thursday. The pressure washing crew will now be continuing everyday until all 119 units are pressure washed on.

Another crew will be added to site starting on the week of July 25th.

Greg
Operations
Cell:604-727-8918