Wednesday, July 27, 2011

Update July 27th


Units 1-91 have been pressure washed. Pressure washing will be complete on all units by the end of next week. Units up to 40 have been completely painted, pending some final deficiency work. Units 41-49 are in progress, and nearing completion. Carpentry work removing the edges of the peak fascia is in progress.

We’re hoping the good weather is here to stay!

-Operations

Saturday, July 16, 2011

Update July 16

We are completing deficiencies on units 25-32. We have the fronts left to paint on units 33-40. We are currently prepping from 41 through 49.

Greg
Operations

Thursday, July 14, 2011

Update

We are currently working on units 41 through 52 pressure washing.

Greg
Operations
We are currently working on units 41 through 52 pressure washing.

Greg
Operations

Monday, July 11, 2011

Update July 11th

Wolfgang deficiencies have been identified on units 21-24 on Sunday. Please leave the green tape up as we fix these. Painting on units 25-28 is wrapping up. We have started painting on units 29-32.

Pressure washing is complete up to unit 40. We will begin pressure washing 41 to 44 starting on Thursday. The pressure washing crew will now be continuing everyday until all 119 units are pressure washed on.

Another crew will be added to site starting on the week of July 25th.

Greg
Operations
Cell:604-727-8918

Wednesday, July 6, 2011

Update - July 6th

Units 21-24 front boom work is being worked on and will be done in the next day of those units and getting ready for inspections.

Unit 25-28 working on the soffits in the back and will be starting front work.

Carpenter has straightened fascia ends on the first 20 buildings and will be back to continue on cutting fascia.

Greg in Operations