Good weather has led to some excellent progress.
Units 1-67 are complete, pending final deficiencies.
Units 68-91 are currently in progress.
For those in units 68-91, if you are able to move your vehicles into your garages for purposes of parking, please do so, as it will speed up the painting of your unit.
-Operations
Friday, August 12, 2011
Wednesday, July 27, 2011
Update July 27th
Units 1-91 have been pressure washed. Pressure washing will be complete on all units by the end of next week. Units up to 40 have been completely painted, pending some final deficiency work. Units 41-49 are in progress, and nearing completion. Carpentry work removing the edges of the peak fascia is in progress.
We’re hoping the good weather is here to stay!
-Operations
Saturday, July 16, 2011
Update July 16
We are completing deficiencies on units 25-32. We have the fronts left to paint on units 33-40. We are currently prepping from 41 through 49.
Greg
Operations
Greg
Operations
Thursday, July 14, 2011
Monday, July 11, 2011
Update July 11th
Wolfgang deficiencies have been identified on units 21-24 on Sunday. Please leave the green tape up as we fix these. Painting on units 25-28 is wrapping up. We have started painting on units 29-32.
Pressure washing is complete up to unit 40. We will begin pressure washing 41 to 44 starting on Thursday. The pressure washing crew will now be continuing everyday until all 119 units are pressure washed on.
Another crew will be added to site starting on the week of July 25th.
Greg
Operations
Cell:604-727-8918
Pressure washing is complete up to unit 40. We will begin pressure washing 41 to 44 starting on Thursday. The pressure washing crew will now be continuing everyday until all 119 units are pressure washed on.
Another crew will be added to site starting on the week of July 25th.
Greg
Operations
Cell:604-727-8918
Wednesday, July 6, 2011
Update - July 6th
Units 21-24 front boom work is being worked on and will be done in the next day of those units and getting ready for inspections.
Unit 25-28 working on the soffits in the back and will be starting front work.
Carpenter has straightened fascia ends on the first 20 buildings and will be back to continue on cutting fascia.
Greg in Operations
604.727.8918
Unit 25-28 working on the soffits in the back and will be starting front work.
Carpenter has straightened fascia ends on the first 20 buildings and will be back to continue on cutting fascia.
Greg in Operations
604.727.8918
Thursday, June 30, 2011
Update June 30
We are finishing off units 15 thru 20 and getting ready for an inspection of 9 through 20. We have started pressure washing on units 21 thru 28 today. The great weather is finally coming!!!!!!
Greg
Operations
Greg
Operations
Friday, June 24, 2011
Update June 24th
We are starting deficiencies on units 1-8. Unit 9-14 will require 6-10 hours work and they will begin deficiencies. We will be working on 14-20 on the next nice day as well. I am waiting for the carpenter to show-up to fix the ends of the facias on some units.
Greg
Operations
Greg
Operations
Wednesday, June 22, 2011
Update June 22
Preparation and priming will begin on units 15-20 today. Final work is being completed on units 1-8. Concern has been brought forward about the straightness of the facias we have cut off. I agree and we will be straightening them up.
Greg
Operations
Greg
Operations
Monday, June 20, 2011
Update June 20, 2011
We plan on having units 1-8 ready for a pre-inspection by end of day Tuesday. We are currently cutting the ends off the soffits on units 9-14 and priming on the front.
Greg
Operations
Cell:604-727-8918
Greg
Operations
Cell:604-727-8918
Thursday, June 16, 2011
Update
The crew is focusing on finishing the first building, Units 1-4. The ends will be cut off the facia boards, today or tomorrow on the first units.
Greg
Operations
Greg
Operations
Wednesday, June 15, 2011
Update
Units 1-20 have been washed. The painting of units 1-4 has been 80% completed. Units 5-8 have been spot primed and we have started to paint them. Once we get a little farther ahead on painting we will be starting to pressure wash again on units 21-30.
Greg
Operations
Cell:604-727-8918
Thursday, June 2, 2011
Sorry!
Power washing was going well today until one of my painters pressure washed units 114 through 119 when notice had been given. I am so sorry! We have stopped on these units and will continue on sequentially.
Sorry,
Greg
Sorry,
Greg
Thursday, May 26, 2011
The start!
We will be pressure washing units 1 through 20 starting on June 1. A notice has been taped to the garage door of the units we are starting with.
We will be using a 15% bleach solution that will not be harmful to your plants.
We will be using a 15% bleach solution that will not be harmful to your plants.
We ask that you please close your windows during the pressure washing phase. We also request you remove all items from your deck and away from the exterior walls. All items that can’t be removed from the deck can be placed in the centre of the deck and covered to allow access to the exterior walls.
We will be working sequentially. Further updates will be made when we move to the next units.
Thanks in advance,
Greg
Wolfgang
Tuesday, May 24, 2011
Thanks!!!!!
Thank you for choosing Wolfgang Commercial Painters to complete your caulking project! Please subscribe to this blog by entering your email address in the Subscribe widget on the right of this post. You will then be sent an email to confirm the activation. Simply click on the link in this email.
We will be posting important information about your project as it proceeds. Once you subscribe, you will be automatically emailed information when updates occur.
Thanks again,
Greg
Operations
Wolfgang
Subscribe to:
Posts (Atom)