Good weather has led to some excellent progress.
Units 1-67 are complete, pending final deficiencies.
Units 68-91 are currently in progress.
For those in units 68-91, if you are able to move your vehicles into your garages for purposes of parking, please do so, as it will speed up the painting of your unit.
-Operations
Friday, August 12, 2011
Wednesday, July 27, 2011
Update July 27th
Units 1-91 have been pressure washed. Pressure washing will be complete on all units by the end of next week. Units up to 40 have been completely painted, pending some final deficiency work. Units 41-49 are in progress, and nearing completion. Carpentry work removing the edges of the peak fascia is in progress.
We’re hoping the good weather is here to stay!
-Operations
Saturday, July 16, 2011
Update July 16
We are completing deficiencies on units 25-32. We have the fronts left to paint on units 33-40. We are currently prepping from 41 through 49.
Greg
Operations
Greg
Operations
Thursday, July 14, 2011
Monday, July 11, 2011
Update July 11th
Wolfgang deficiencies have been identified on units 21-24 on Sunday. Please leave the green tape up as we fix these. Painting on units 25-28 is wrapping up. We have started painting on units 29-32.
Pressure washing is complete up to unit 40. We will begin pressure washing 41 to 44 starting on Thursday. The pressure washing crew will now be continuing everyday until all 119 units are pressure washed on.
Another crew will be added to site starting on the week of July 25th.
Greg
Operations
Cell:604-727-8918
Pressure washing is complete up to unit 40. We will begin pressure washing 41 to 44 starting on Thursday. The pressure washing crew will now be continuing everyday until all 119 units are pressure washed on.
Another crew will be added to site starting on the week of July 25th.
Greg
Operations
Cell:604-727-8918
Wednesday, July 6, 2011
Update - July 6th
Units 21-24 front boom work is being worked on and will be done in the next day of those units and getting ready for inspections.
Unit 25-28 working on the soffits in the back and will be starting front work.
Carpenter has straightened fascia ends on the first 20 buildings and will be back to continue on cutting fascia.
Greg in Operations
604.727.8918
Unit 25-28 working on the soffits in the back and will be starting front work.
Carpenter has straightened fascia ends on the first 20 buildings and will be back to continue on cutting fascia.
Greg in Operations
604.727.8918