Thursday, June 30, 2011

Update June 30

We are finishing off units 15 thru 20 and getting ready for an inspection of 9 through 20. We have started pressure washing on units 21 thru 28 today. The great weather is finally coming!!!!!!

Greg
Operations

Friday, June 24, 2011

Update June 24th

We are starting deficiencies on units 1-8. Unit 9-14 will require 6-10 hours work and they will begin deficiencies. We will be working on 14-20 on the next nice day as well. I am waiting for the carpenter to show-up to fix the ends of the facias on some units.

Greg
Operations

Wednesday, June 22, 2011

Update June 22

Preparation and priming will begin on units 15-20 today. Final work is being completed on units 1-8. Concern has been brought forward about the straightness of the facias we have cut off. I agree and we will be straightening them up.

Greg
Operations

Monday, June 20, 2011

Update June 20, 2011

We plan on having units 1-8 ready for a pre-inspection by end of day Tuesday. We are currently cutting the ends off the soffits on units 9-14 and priming on the front.

Greg
Operations
Cell:604-727-8918

Thursday, June 16, 2011

Update

The crew is focusing on finishing the first building, Units 1-4. The ends will be cut off the facia boards, today or tomorrow on the first units.

Greg
Operations

Wednesday, June 15, 2011

Update

Units 1-20 have been washed. The painting of units 1-4 has been 80% completed. Units 5-8 have been spot primed and we have started to paint them. Once we get a little farther ahead on painting we will be starting to pressure wash again on units 21-30.

Greg
Operations
Cell:604-727-8918

Thursday, June 2, 2011

Sorry!

Power washing was going well today until one of my painters pressure washed units 114 through 119  when notice had been given. I am so sorry! We have stopped on these units and will continue on sequentially.

Sorry,
Greg